AIP Supplement for HUNGARY

HUNGAROCONTROL

AIRAC

AIP SUP

001/2022

Effective from 03 NOV 2022 to 13 JUL 2023

Published on 22 SEP 2022

  Budapest Liszt Ferenc International Airport (LHBP) Cargo Apron development works

1.   GENERAL

The development works of LHBP Cargo Apron includes:

2.   PERIOD OF CONSTRUCTION

The development project will started in Q3 2022 and the competition is scheduled for the Q3 2023. The works are phased and the relevant information for each phase will be disseminated by AIP supplement and activated by NOTAM. The actual closure restrictions will be published by NOTAM.

3.   PHASE A

Commence and actual finish of the phase will be notified by NOTAM.

Involved areas: Whole Apron Cargo, stand C1, C1L/R, C2, C2L/R, Taxiway E, Taxiway A8, A9.

3.1   TRAFFIC INFORMATION AND RESTRICTIONS

Restrictions on parking stands at Cargo Apron:

  • Whole Cargo Apron is CLOSED!
  • All Cargo flight will be relocated to Apron 2, and RWY 13L/31R.
  • At Apron 2 due to alternate parking, all cargo ACFT is escorted by FOLLOW ME and positioned by Marshaller.
  • On RWY 13L/31R due to alternate parking all aircraft is escorted by FOLLOW ME and positioned by towing truck supervised by Marshaller.
  • Due to reduced safety distance between service road and TWY A8-A9, all ACFT with wingspan higher than 36 M will be escorted by FOLLOW ME on TWY A8-A9.

4.   PHASE B

Commence and actual finish of the phase will be notified by NOTAM.

Involved areas: Whole Apron Cargo, stand C1, C1L/R, C2, C2L/R, Taxiway E, Taxiway A8, A9.

4.1   TRAFFIC INFORMATION AND RESTRICTIONS

Restrictions on parking stands at Cargo Apron:

  • All ACFT arriving to stand C1, C1L/R, C2, C2L/R, has to stop on TWY E. After engine shut down the ACFT will be towed into final parking position.
  • Silent push and pull procedures shall be followed from stand C1, C1L/R, C2, C2L/R. All ACFT will be towed to abeam stand C1 where the engine start allowed.
Figure 1.  Construction phases
PDF../graphics/eSUP/2022-01-construction_phases.pdf